Architects Selected

The board selected Helman Hurley Charvat Peacock Architects, Inc. (HHCP) to put together the convention center drawings.
Details Revealed

Made public details about the proposed project and exterior renderings.
Groundbreaking Ceremony

The East Montgomery County Improvement District Board of Directors celebrated the official groundbreaking of the 210,000-square-foot convention center on Monday, March 10 in Valley Ranch Town Center. The groundbreaking ceremony featured speakers including Frank McCrady, President/CEO of EMCID; Commissioner Matt Gray’s Office, Montgomery County Precinct 4; Michael Chatham with HHCP Architects | a GHC Orcutt Winslow Company; Aaron Bradford, Operations Manager, SpawGlass; and Greg Wattson, Senior Vice President, Commercial Development at the Signorelli Company.
The Convention Center Goes Vertical


EMCID’s Convention Center is vertical! Postel Erection Group raised the first tilt wall August 11, 2025, as construction on the 210,000-square-foot convention center steadily progresses. Walls went up on the offices and the kitchen area.
Excavation Begins in Parking Garage
Excavation begins on the 800+ space parking garage adjacent to the Convention Center.
Topping Out Ceremony
![]()
![]()
EMCID, SpawGlass, and dozens of others involved in the creation and construction of the district’s 210,070-square-foot convention center participated in a Topping Out Ceremony November 20, 2025. This commemorates a major construction milestone of completing the structural frame and celebrates progress toward finishing the building. For the ceremony, a steel beam was painted so that the project team, construction crews, and EMCID board and staff could sign the beam. The beam was then hoisted into place, completing the frame of the building.
![]()